June 30th 2024
 

Mountain Bike Trail Maintenance Report

 

Date: June 30, 2024

 

Trail Name: Berm Burner

 

Location: Hemlock Stone Trail

 

Committee Members Present: 2

 

Volunteers: 1

Weather and Ground Conditions

•⁠  ⁠Weather: Dry

•⁠  ⁠Ground Conditions: Hard, making it difficult to justify using the full set of tools

 

Maintenance Activities

Despite the challenging dry conditions, some urgent maintenance was successfully conducted on the new "Berm Burner" catch berm.

 

Activities Undertaken:

•⁠  ⁠Drainage Solution: The main focus was on installing a drainage solution for the berm. This was a high-priority task to ensure proper water runoff and prevent future erosion.

  

Completion Status:

•⁠  ⁠The drainage solution has been successfully implemented.

•⁠  ⁠Local riders have tested the berm and confirmed the effectiveness of the remediation.

 

Tools and Equipment Used

•⁠  ⁠Due to the hard ground conditions, only essential tools were used.

 

Observations

•⁠  ⁠The dry conditions made it difficult to perform extensive trail work.

•⁠  ⁠The berm's reinstatement appears to be effective based on feedback from local riders.

 

 

Next Steps:

•⁠  ⁠Monitor the effectiveness of the drainage solution during the next rainfall.

•⁠  ⁠Plan for additional maintenance work when ground conditions improve to ensure ongoing trail integrity.

 

Prepared by:

Paul Barker  

HTA Treasurer  

June 30, 2024

photos
 

Notebook Dried Plants

dirt diary.

See our previous dirt diaries

Get Monthly Updates

Keep in the loop with all things Hemlock Trail Association! 

Thanks for submitting!

bottom of page